Application for New Building Permit

Secure your official Building Permit from the Office of the Building Official before starting any construction, renovation, or demolition project.

Overview

Service Summary

Key information you need before starting this service.

Processing

15 Working Days (Complex)

Fee

Computed per sq.m. (National Building Code)

Who Can Apply

Property Owners or Authorized Representatives

Application

Walk-in

Process

Step-by-Step Process

Follow these steps to complete this service.

1

Submit & Routing

Submit your complete plans and legal documents to the Office of the Building Official. Your application will be reviewed by the municipal engineering team (Architectural, Structural, Electrical, and Plumbing) for technical approval.

2

Assessment & Clearances

Once technically approved, you will receive an Order of Payment. You will also need to submit your documents to the Bureau of Fire Protection to get your Fire Safety Evaluation Clearance.

3

Pay Fees

Pay your computed Building Permit fees at the Municipal Treasurer's Office and secure your Official Receipt.

4

Claim Permit

Final Step

Return to the Office of the Building Official with your Official Receipt and Fire Safety Clearance to claim your signed Building Permit and stamped plans.

Checklist

Requirements

Prepare these documents before submitting your application.

Legal Documents

3 items to prepare

  • Certified True Copy of your Transfer Certificate of Title from the Registry of Deeds.
  • Tax Declaration and your latest Real Property Tax (Amilyar) Receipt.
  • If you are not the registered owner: A Notarized Contract of Lease, Deed of Absolute Sale, or a written Consent to Construct from the lot owner.

Technical Documents (Signed & Sealed)

4 items to prepare

  • Five (5) sets of complete Building Plans (Architectural, Structural, Sanitary/Plumbing, Electrical, Mechanical).
  • Three (3) sets of Bill of Materials and Cost Estimates.
  • Three (3) sets of General Specifications.
  • For 2-story buildings and above: Structural Analysis and Design.

Clearances

3 items to prepare

  • Barangay Clearance specifically issued for a Construction or Building Permit.
  • Locational or Zoning Clearance from the Municipal Planning and Development Office.
  • Fire Safety Evaluation Clearance from the Bureau of Fire Protection.

Help

Frequently Asked Questions

Quick answers to common questions about this service.

Office

Office Information

Contact or visit the responsible office for assistance.

Office of the Building Official

Municipal Hall

engineering@binangonan.gov.ph

Monday to Friday, 8:00 AM - 5:00 PM

Cost to the People and Government of Binangonan: ₱0